MS9 |
User prototype archive review |
WP2, WP3 |
UEDIN |
01/10/2015 |
Completed (with delay, as described in the previous report) by the beta-testing group of the Gaia archive. |
MS8 |
Mid-term review |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/06/2015 |
Plenary meeting to take place in Sept in Barcelona. Mid term review in Nov. 2015 in Leiden (agreed with PO during the 1st year review) |
MS7 |
Public version of GENIUS portal |
WP6, WP7 |
CSUC |
01/10/2014 |
Public version of GENIUS portal |
MS6 |
Requirements document for each subsystem |
WP2, WP3, WP4, WP5 |
UB |
01/10/2014 |
WP3 SRS |
MS5 |
Archive user requirements document |
WP2 |
UL |
01/10/2014 |
|
MS4 |
GENIUS portal available at CESCA for internal use |
WP6, WP7 |
CSUC |
01/04/2014 |
Two GENIUS portal developed at CESCA: one dedicated to the project and one for more general dissemination. |
MS3 |
Hiring of main developers |
WP1, WP2, WP3, WP5, WP4, WP6, WP7 |
UB |
01/06/2014 |
|
MS2 |
Agreed testbed environment with ESAC-SAT & CU9 |
WP3 |
UEDIN |
01/02/2014 |
The testbed for Archive development has been agreed with SAT. And is based on the Gaia Archive Core System (GACS) described at the CU9 SDP.. |
MS17 |
Handover of GENIUS portal to Gaia community |
WP7 |
CSUC |
01/04/2017 |
Handover of GENIUS portal to Gaia community |
MS16 |
GENIUS products availability |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/04/2017 |
GENIUS products availability |
MS15 |
Completion meeting & final external review |
WP1 |
UB |
01/03/2017 |
|
MS14 |
Load of actual Gaia data |
WP3, WP5 |
CNRS |
01/01/2017 |
Load of actual Gaia data |
MS13 |
Stress test |
WP3 |
UEDIN |
01/09/2016 |
A test suite has been designed to stress test the system and details of this along with results for the GENIUS prototype querying system are in the process of being documented (http://gaia.esac.esa.int/dpacsvn/DPAC/CU9/docs/WP930_Architecture/nonECSS/TechNotes/GAIA-C9-TN-IFA-STV-001/GAIA-C9-TN-IFA-STV-001.pdf) Formal attainment of milestone MS13 has been delayed to the end of the year (31/12/2016) owing to delays in prototype deployment of the full distributed querying system. These delays were caused in part by refactoring of the various subsystems into Docker-deployable containers along with higher priority work in collaboration with Gaia DPAC CU9 and ESAC-ESDC concerning Gaia DR1 data model issues and VO integration work (content descriptors and ADQL language etc.) |
MS12 |
Prototype archive tools open to community |
WP1, WP2, WP3, WP4, WP5, WP6, WP7 |
UB |
01/10/2015 |
User testing will allow to give the necessary feedback on the archive tools which have been developed. Most Gaia data will not be available at the date of the milestone, but the testing will nevertheless be possible by providing access to simulated data. In order to get a feedback as large as possible on the archive tools, the access will be given to a large panel of users within and outside the Gaia community. They will e.g. be selected among the users having made requirements proposals (cf. GAIA-C9-TN-LEI-AB-026-1). |
MS11 |
Validation tools review |
WP2, WP5 |
CNRS |
01/10/2015 |
Specific session during CU9 plenary meeting Sept. 2015: https://gaia.am.ub.es/Twiki/bin/view/GENIUS/PlenaryMeeting2015 |
MS10 |
Exploitation tools review |
WP2, WP4 |
UB |
01/10/2015 |
Specific session during CU9 plenary meeting Sept. 2015: https://gaia.am.ub.es/Twiki/bin/view/GENIUS/PlenaryMeeting2015 |
MS1 |
Kick-off meeting (plenary) |
WP1 |
UB |
01/11/2013 |
Meeting took place 4-5 Dec 2013 |